ATLANTIC HIGHLANDS, NJ -The Atlantic Highlands-Highlands Regional Sewerage Authority is doing work on the Force Main along a stretch of Monmouth Avenue.  Below is the Force Main Project update for the next two weeks

Monday July 29 through Thursday August 1 (no work Friday August 2, 2013).  Excavation of Sears Avenue, starting at Monmouth Avenue and ending just beyond the tennis courts.  There will also be project clean-up and maintenance along Monmouth and Navesink Avenue.  Detours and traffic delays should be expected between 7 AM and 5:30 PM.

Monday August 5 through Thursday August 8 (no work Friday August 9, 2013). Project clean-up and maintenance along Monmouth, Navesink and Sears Avenues.  Detours and traffic delays should be expected between 7 AM and 5:30 PM.

The schedule above may be affected by weather and other factors.  There will be no road construction on weekends.

The areas excavated each day will be closed and repaved by the end of that day.  Passage for emergency & service vehicles, school buses and local traffic will be maintained at all times but delays could occur so alternate routing is advised if possible.