JULY 3, 2013

NOTICE TO RESIDENTS

Roadway construction for the sanitary sewer line replacement project is scheduled in your immediate area over the next few days. Additional details are included in the Notice of Road Construction previously mailed to every postal customer in the area.The schedule below may be affected by weather and other factorsso please check the electronic sign boards for any updates. There will also be Middletown Police Officers on site for traffic safety and they will have additional information about how the work throughout the day will affect your specific area.Access to side streets and to individual driveways may be limited during a portion of the period shown below (residents who are directly affected will be notified the day before).

Please park cars away from the scheduled work area and consider alternatives for times when your driveway or side street may be inaccessible.Passage for emergency & service vehicles, school buses and local traffic will be maintained at all times but delays could occur so alternate routing is advised if possible.The areas excavated each day will be closed and repaved by the end of that day. A final roadway milling and repaving will be done about three months after completion (this is a required waiting period to allow for any ground settling).For any questions or issues pertaining to individual properties you can contact the project on-site inspector Alex Kolodziejczyk, T&M Associates, at 732-241-6283 or the project manager Rich Mitchell, Mount Construction, at 609-477-6290. For general questions or any unresolved issues you can contact the AHHRSA Administrator, David Palamara, at 732-291-3030; he will be available during the day and evenings or by email at This email address is being protected from spambots. You need JavaScript enabled to view it..

Work plans for the next TWO WEEKS include:

Monday, July 8 through Thursday, July 11 (no work will be done on Friday July 12).  Excavation of the northerly lane of Monmouth Avenue, between Valley Drive and Lakeside Avenue.  Detours and traffic delays should be expected between 7 AM and 5:30 PM. 

Monday, July 51 through Thursday, July 18 (no work will be done on Friday July 16).  Excavation of the northerly lane of Monmouth Avenue, between Lakeside Avenue and Sears Avenue.  Detours and traffic delays should be expected between 7 AM and 5:30 PM. 

The schedule above may be affected by weather and other factors.  There will be no road construction on weekends.

The areas excavated each day will be closed and repaved by the end of that day.  Passage for emergency & service vehicles, school buses and local traffic will be maintained at all times but delays could occur so alternate routing is advised if possible.